Devanahalli: About 70 per cent work on the Bangalore International Airport will be completed by yearend with evacuation work already starting on the portions that are to be expanded.
The newly redesigned airport will meet the opening date of April 2, 2008, with cost escalation of Rs 530 crore which will be met through loans, deputy CM B S Yediyurappa said during a site review on Thursday.
Bangalore International Airport Limited CEO Albert Brunner, who along with his officials, escorted the DyCM around the site, said 23 per cent of the work is over as on date.
Work on the site is on full swing with large sections of the boundary wall completed.
08/06/06 Times of India
To Read the News in full at Source, Click the Headline
Friday, June 09, 2006
Home »
» Bangalore International airport dreams draw closer
Bangalore International airport dreams draw closer
Friday, June 09, 2006
Related Posts:
Salem airport remains inactiveSalem: Despite being witness to a flurry of development activities for a staggering Rs. 3,000 crore, Salem airport remains inactive. It is wearing the… Read More
Bigger Jet Airways plane for Chennai-KL routeSepang: Jet Airways (India) Ltd is flying aircraft with increased passenger capacity of nearly 60% for its Chennai-Kuala Lumpur route to accommodate r… Read More
AAPI forges stronger alliance with Air IndiaNew York: Dr Hemant Patel, President of American Association of Physicians of Indian Origin (AAPI) and core members such as Dr Jayesh Kanuga and Dr Se… Read More
India, China should lead world aviation sector: IATA chiefNew Delhi: India and China, emerging as giants in the global aviation industry, need to be innovative and should not follow Europe that has been lax i… Read More
Jet Airways hopeful of wider collaboration with MASSepang: Jet Airways (India) Ltd hopes a wider collaboration with national carrier Malaysian Airline System Bhd (MAS) will materialise by the middle of… Read More
0 comments:
Post a Comment